1. Which of the following depend(s) on the WBS? a. schedule b. Work package esti

ID: 404356 • Letter: 1

Question

1. Which of the following depend(s) on the WBS?

a. schedule

b. Work package estimates

c. Uncertanity analysis

d. All of the above

e. A and C

f. A, B, and C


2. What is the correct equation to use when employing the PERT time estimation method?


3. Which WBS approach is most likely to leave team members with individual views of the work packages, but not an entire view of the project?

a. Mind mapping

b. Top Down approach

c. Bottom-Up Approach

d. All of the above share this risk

e. None of the above have this risk


4. The _________________ method is best suited for use in uncertainty assessment when team members are located at different sites and cannot meet face-to-face?


5. Which of the following does a team typically consider during uncertainty assessment?

a. Favorable uncertaintie

b. Unfavorable uncertainties

c. Statistical probability of the occurrence of each uncertainty

d. Unknown unknowns

e.  A and B only

f.  C and D only


6. Which of the following is NOT a simulation tool?

a. Physical mock-up

b. Dress rehearsal

c. Monte Carlo

d. Tabletop exercise

e. None of the above: all are simulation tools


7. The government of an unnamed country has assigned a project team to initiate and run a program to create jobs. The program will include job training, career counseling, unemployment payments, and hiring incentives for employers. During the team

Explanation / Answer

ans1) d,f 3:a 4:

ans6) c