Development of an update of a particular software product is being considered by
ID: 402829 • Letter: D
Question
Development of an update of a particular software product is being considered by a software house. Information on the activities necessary for the completion of this project is provided in the following table:
Activity
Immediate
Predecessors
Normal Time
(Weeks)
Crash Time
(Weeks)
Normal Cost
Crash Cost
A
--
6
1
$400
$1,000
B
--
3
1
$200
$300
C
--
4
4
$310
$310
D
A
6
5
$100
$300
E
B
4
2
$200
$300
F
C
3
2
$150
$180
G
D, E
2
1
$600
$800
Verify that the critical path using the normal time for each activity is A, D, G, and the minimum project duration in weeks is 6+6+2. Then answer the following question: What is the minimum cost of reducing project duration by one week?
Activity
Immediate
Predecessors
Normal Time
(Weeks)
Crash Time
(Weeks)
Normal Cost
Crash Cost
A
--
6
1
$400
$1,000
B
--
3
1
$200
$300
C
--
4
4
$310
$310
D
A
6
5
$100
$300
E
B
4
2
$200
$300
F
C
3
2
$150
$180
G
D, E
2
1
$600
$800
Explanation / Answer
Min cost of reducing project duration by one week=$300
because D can be reduced to 5 weeks by using crash time.