Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

1A) Which of the following would not be considered a cost of Internal Equity? Im

ID: 394184 • Letter: 1

Question

1A) Which of the following would not be considered a cost of Internal Equity?

Implied cost using the Dividend Discount Model (DDM)

Zero cost

Opportunity cost of alternative investments to the company

Implied cost using CAPM

1B) Oldguy Inc. is considering two independent investments with the following cash flow streams:

initial

Year 1

Year 2

Year 3

Year 4

Year 5

Proj A

-50,000

+20,000

+20,000

+10,000

+5,000

+5,000

Proj B

-50,000

+10,000

+10,000

+5,000

+5,000

+50,000

Oldguy uses a combination of NPV and Payback period to evaluate alternatives, with a requirement of a positive NPV using a 10% discount rate and a maximum payback of 3 years. Which project(s) should Oldguy select?

A and B

neither A nor B

B only

A only

a.

Implied cost using the Dividend Discount Model (DDM)

b.

Zero cost

c.

Opportunity cost of alternative investments to the company

d.

Implied cost using CAPM

Explanation / Answer

1A b. Zero cost. Correct option

1B Project A NPV = 20000/1.10 + 20000/1.102 + 10000/1.103 + 5000/1.104 + 5000/1.105 – 50000

Project A = -1256.43 $

Project B payback is greater than 3 years as only 25000 cash flow comes to the organization in first three years.

b. Neither A nor B. Correct option

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote