Please answer Questions 1, Question 2, Question 3, Question 4, and Question 5. I
ID: 3868524 • Letter: P
Question
Please answer Questions 1, Question 2, Question 3, Question 4, and Question 5. I have each Question in bold so you will be easily able to tell each question. When you answer the 5 questions please show detailed steps along with caluclations so I can see how you came up with the answer. Again, please answer ALL 5 QUESTIONS, showing CALCULATIONS and detailed STEPS, as well as the ANSWERS. Question 1: Use the following for the next five questions: The following data is given for the Walker Compan Budgeted production.1,000 units Actual product Materials: 980 units $2.00 Standard price per lb Standard pounds per completed unit Actual pounds purchased and used in production.1,800 Actual price paid for materials $23,000 Labor: Standard hourly labor rat.14 per hour Standard hours allowed per completed unit...4.5 Actual labor hours worked..4,560 Actual total labor costs..2,928 The direct material price variance is: A) S600 F B) S600 U C) $80 F D) $80 UExplanation / Answer
ANSWERS
1.Direct material price variance = (SP-AP)*AQ
=[$2.00-($23000/1100)]* 11800
= ($2.00-1.9491)* 11800
=$600 F
aswer is A.
2. direct material quantity variance = (SQ-AQ) * SP
=[(12 * 980)- 11800] * $2.00
=$80 U
answer is D
3. Direct labor rate variance = (SR-AR) * AH
=[$14 - ($62928/4560)] * 4560
=$912 F
answer is B
4. Direct labor efficiency variance = (SH - AH) * SR
=[(4.5 * 980) - 4560] * $14
=$2100 U
answer is C
5. Total direct labor variance = $912F + $2100 U
=$1188 U
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.