What is the first thing that should happen when a new change request comes in? I
ID: 3857500 • Letter: W
Question
What is the first thing that should happen when a new change request comes in?
It should be evaluated for feasibility
It should be assigned a tracking number
A determination is made as to whether the person or entity submitting the change request is a valid stakeholder in the project
The project sponsor is notified
A.It should be evaluated for feasibility
B.It should be assigned a tracking number
C.A determination is made as to whether the person or entity submitting the change request is a valid stakeholder in the project
D.The project sponsor is notified
Explanation / Answer
First we need to authorize the request, that it is coming from an authentic person who has the right to request for change. Then its feasibility can be checked and project sponsor should be notified. Then we can assign it a tracking number.
So (C) should be the first thing to do.