Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

1. Which of the following strategies is not used for negative risks? Transfer Av

ID: 381381 • Letter: 1

Question

1.     Which of the following strategies is not used for negative risks?

Transfer

Avoid

Exploit

Mitigate

5 points   

QUESTION 2

1.     Conflict management techniques that may be used on a project include confronting, smoothing, forcing, and:

withdrawing

directing

organizing

controlling

5 points   

QUESTION 3

1.     A group of related projects is known as a(n):

Project

Operations

Program

Portfolio

5 points   

QUESTION 4

1.     Which of the following is not an example of Organizational Process Assets

Policies

Procedures

Government Regulation

Lessons Learned

5 points   

QUESTION 5

1.     During which phase of the project will risks be the highest?

Initiating

Planning

Execution

Closing

5 points   

QUESTION 6

1.     Which is one example of Crashing?

Starting a few activities simultaneously

Adding more resources

Reducing resources

Increasing the duration of the project

5 points   

QUESTION 7

1.     You want to group your project stakeholders based on their authority and involvement in the project. Which of the following is appropriate for this?

Power/Interest Grid

Power/Influence Grid

Influence/Impact Grid

Power/Impact Grid

5 points   

QUESTION 8

1.     During which risk management process is a determination to transfer a risk made?

Identify Risks

Perform Quantitative Risk Analysis

Plan Risk Response

Monitor and Control Risks

5 points   

QUESTION 9

1.     Which document is created by breaking the project scope into smaller manageable elements?

Scope Baseline

OBS

WBS

None of the above

5 points   

QUESTION 10

1.     Which of the following is not an output of a project?

Developing a new car

The production of cars

An enhancement to the car

Completing research on a car

5 points   

QUESTION 11

1.     An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late (LF) of day 19. The activity :

is on the critical path

has a lag

is progressing well

is not on the critical path

5 points   

QUESTION 12

1.     Which of the following is not true?

Every project is unique

A project is unique

Projects are not repetitive

Car manufacturing is an example of a project

5 points   

QUESTION 13

1.     The most important part of stakeholder management is:

Ensuring all stakeholders are communicated with the same

Good relationships are established with all stakeholders

Challenging stakeholders are avoided and added to the risk register

Changes are made to the project schedule

5 points   

QUESTION 14

1.     During risk management activities, 236 risks have been identified which are caused by 13 root causes. You could eliminate 234 risks by your risk management activities. For the remaining 2 risks, you, together with your team, could not find a way to mitigate or insure the risks. Also these 2 risks cannot be outsourced or removed from the project scope. What is the best solution?

Transfer the risk

Mitigate the risk

Avoid the risk

Accept the risk

5 points   

QUESTION 15

1.     You are a new project manager who has never managed a project before. It would be best in this situation to rely on _______ during planning in order to improve your chances of success.

Your intuition and training

Stakeholder analysis

Historical information

Configuration management

5 points   

QUESTION 16

1.     A project has more than one critical path. What does this mean to you?

Risk increases

Risk decreases

The duration of the project is reduced

The project may cost less

5 points   

QUESTION 17

1.     What is the most important criterion when an organization chooses a project-selection model?

Organizational fit

Flexibility

Cost

Capability

5 points   

QUESTION 18

1.     Your project is late and to bring it back on track you are adding extra resources to some activities and giving overtime to your team members. This is an example of:

Critical Chain

Fast Tracking

Resource Leveling

Crashing

5 points   

QUESTION 19

1.     Which of the following risks will be managed with the Contingency Reserve?

Known Risks

Unknown Risks

Low Priority Risks

High Priority Risks

5 points   

QUESTION 20

1.     In which phase(s) do you identify project stakeholders?

Initiating, Planning, Execution

Initiating and Planning

Initiating, Planning, and Monitoring & Controlling

All phases


Transfer

Avoid

Exploit

Mitigate

Explanation / Answer

1. Exploit. Negative risk strategies are transfer avoid mitigate and accept.

2. Withdrawing. It is better to walk away when people frustrate.

3. Program. A coordinated group of related projects

4. Govt regulation. This is not specific to organization