The following table shows the estimated velocity, actual velocity and available
ID: 3798610 • Letter: T
Question
The following table shows the estimated velocity, actual velocity and available man-days for the first sprint.
First Sprint
Second Sprint
Estimated Velocity : 26
Actual Velocity : 18
Available Man-days : 36
Estimated Velocity : ?
Actual Velocity :
Available Man-days : 50
When the available man-days of next sprint is 50. Compute the final estimated velocity for second Sprint.
Hint: Available man-days * focus factor = estimated velocity
First Sprint
Second Sprint
Estimated Velocity : 26
Actual Velocity : 18
Available Man-days : 36
Estimated Velocity : ?
Actual Velocity :
Available Man-days : 50
Explanation / Answer
first sprint:
Focus factor = Estimated velocity / Available man days
Focus factor = 26 / 36
second sprint:
Estimated velocity = Available man days * Focus factor
= 50 * 26/36 = 36.1 ~ 36
Estimated velocity in second sprint = 36