Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following table shows the estimated velocity, actual velocity and available

ID: 3798610 • Letter: T

Question

The following table shows the estimated velocity, actual velocity and available man-days for the first sprint.

First Sprint

Second Sprint

Estimated Velocity : 26

Actual Velocity : 18

Available Man-days : 36

Estimated Velocity : ?
Actual Velocity :
Available Man-days : 50


When the available man-days of next sprint is 50. Compute the final estimated velocity for second Sprint.

Hint: Available man-days * focus factor = estimated velocity

First Sprint

Second Sprint

Estimated Velocity : 26

Actual Velocity : 18

Available Man-days : 36

Estimated Velocity : ?
Actual Velocity :
Available Man-days : 50

Explanation / Answer

first sprint:

Focus factor = Estimated velocity / Available man days

Focus factor = 26 / 36

second sprint:

Estimated velocity = Available man days * Focus factor

                             = 50 * 26/36 = 36.1 ~ 36

Estimated velocity in second sprint = 36

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote