2. Earned Value Management A. Using the plan data in the table below, complete t
ID: 379411 • Letter: 2
Question
2. Earned Value Management A. Using the plan data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June. Complete the earned value column on the right. Assume the project is planned for a 12-month duration and $250,000 budget. Earned Value Activity Jan Feb Mar Apr May Jun Plan % Complete 15100% 100% 70% 67% 3032 25% Staffing 8 7 2 10 10 3 8 10 21 Blueprinting Prototype Full Design Construction Transfer Monthly Plan: Cumulative: 7 cHint this one is computed for you 41 42 10 10 Total: 45 Monthly Actual: 10 15 6 14 9 40 47 Cumul. Actual: Sheet1Explanation / Answer
P * % comp Jan Feb Mar Apr May Jun Plan %comp EV Staff 8 7 15 100% 15 BP 4 6 10 100% 10 Proto 2 8 10 70% 7 Full design 3 8 10 21 67% 14.07 Construc 2 30 32 25% 8 Transfer 10 10 0% 0 sum of all activity Monthly plan 8 11 8 11 10 50 Total 54.07 Total till this time Cummulative 8 19 27 38 48 98 Monthly Act 10 15 6 14 9 40 Total Act till this time Comm Act 10 25 31 45 54 94
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.