Question 44 (4.5 points) An activity on a PERT network has these time estimates:
ID: 379175 • Letter: Q
Question
Question 44 (4.5 points) An activity on a PERT network has these time estimates: optimistic 2, most likely- 3, and pessimistic-8. Its expected time and variance (if is a critical activity) are 1) none of these 2) 3.67;6 3) 3.67; 1 4) 4.33:6 5) 4.33; 1 Save Question 45 (4.5 points) A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the crtical path is 90 days with a project variance of 25, the 0.3446 2) 0.6554 3) 18 4) 0.0228 5) 0.9772Explanation / Answer
44. 3. Te=3.67, Te= expected time=(a+4*m+b)/6, and Variance=1 ((8-2)/6)^2)
45. 3. 18%
Probability calculation
z=(specified time-path expected time)/variance
-0.89
=(88-90)/SQRT(5)
18.55%
=NORMSDIST(-0.89)
Probability calculation
z=(specified time-path expected time)/variance
-0.89
=(88-90)/SQRT(5)
18.55%
=NORMSDIST(-0.89)
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.