Question 44 (4.5 points) An activity on a PERT network has these time estimates:

ID: 379175 • Letter: Q

Question

Question 44 (4.5 points) An activity on a PERT network has these time estimates: optimistic 2, most likely- 3, and pessimistic-8. Its expected time and variance (if is a critical activity) are 1) none of these 2) 3.67;6 3) 3.67; 1 4) 4.33:6 5) 4.33; 1 Save Question 45 (4.5 points) A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the crtical path is 90 days with a project variance of 25, the 0.3446 2) 0.6554 3) 18 4) 0.0228 5) 0.9772

Explanation / Answer

44. 3. Te=3.67, Te= expected time=(a+4*m+b)/6, and Variance=1 ((8-2)/6)^2)

45. 3. 18%

Probability calculation

z=(specified time-path expected time)/variance

-0.89

=(88-90)/SQRT(5)

18.55%

=NORMSDIST(-0.89)

Probability calculation

z=(specified time-path expected time)/variance

-0.89

=(88-90)/SQRT(5)

18.55%

=NORMSDIST(-0.89)