7. value: 1.36 points Conceptual Question 19-8 Which of the following statements is correct... Which of the following statements is correct with respect to slack time? OThe slack time of an activity is the latest completion time of the activity minus the earliest completion time. OThe slack time of an activity is the latest start time of the activity minus the earliest start time. OThe slack time of an activity determines by how much an activity can be delayed without impacting the overall completion of the project. OAll of these statements are correct.

Explanation / Answer

7.

19-8. The correct answer is "All of these statements are correct".

Slack time refers to the time by which a task can be delayed without affecting the another task or completion of the project. The difference between latest completion time and earliest completion time or the difference between the latest start time of activity and earliest start time is the slack time of an activity.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote