The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 u

ID: 377785 • Letter: T

Question

The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 2 weeks to make T, 2 weeks to make U 1 week to make V, 2 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 1 week to make Z. a) Choose the correct product structure A. Level Level Level Level Ul

Explanation / Answer

Solution :

Correct option is option : D

All other are incorrect.

Option A : Child of T are V, W, X

Option B : Child of S are T and U

Option C : Child of S are T and U