Based on a careful work study in the Hofstetter Corp., the results shown in the following table have been observed: Performance Rating 120% 115% 95% 90% Observation (minutes per cycle) Element 3 34 36* 4 20 2 4 40 13 Prepare daily reports Photocopy results Label and package reports Distribute reports 34 12 4 15 39 2 18 46A Photocopying machine broken; included as delay in the allowance factor A Power outage; included as delay in the allowance factor The allowance factor for this type of work is given to be 12%. (Round all intermediate calculations to two decimal places before proceeding with further calculations.) a) The normal time for the "prepare daily reports" operationminutes (round your response to two decimal places)Explanation / Answer
a- Performance rating in "prepare daily report" is 120% it means the effciency in the process is 20% more than the standrad time.
Average time for "prepare daily report" = (34+39+34+41+40)/5=188/5=37.6 minutes .
Normal time=37.6*1.2=45.12 minutes
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.