91 6. Complexity Cost Weightin 93 Consider the data provided below and compute t

ID: 375604 • Letter: 9

Question

91 6. Complexity Cost Weightin 93 Consider the data provided below and compute the total estimated of function points Function Input Output Interfaces Queries High High Medium 100 Complexity Weighting 102 103 104 105 106 107 108 Function Low Medium High Total Input Output Interfaces Queries Files 2 x 12 x 12 x 4 x 8 x Calculate the total expected cost of the project: Assume that each resource can complete five function points per month and each programmer costs $4,000 per month. Total Number of Functions: Total Number of person-months needed: Total cost for the Project: Sheet1 114 Ready

Explanation / Answer

Total expected cost of the project = 444 * $4000 = $1,776,000

Function Low Medium High Total Input 2x8 16 Output 3x6 18 Interfaces 18x15 270 Queries 8x5 40 Files 4x25 100