1. Explain how bar charts and activity network diagrams provide different views

ID: 3750137 • Letter: 1

Question

1. Explain how bar charts and activity network diagrams provide different views of a project's schedule and tasks. 2. Describe the Critical Path Method (CPM)/Critical Path Analysis (CPA) that is commonly used in engineering and construction projects for scheduling and planning 3. The table below defines the activities for a small project Task Completion time Dependencies (weeks) B. A a. Draw a network diagram (i.e., Pert Chart) for the above project. Use Microsoft Visio or a similar drawing tool. b. What is the critical path for this project? c. How many weeks will it take to complete the project if everything stays on schedule?

Explanation / Answer

Please Note: I have answered the first question, according to Chegg Answering Guidelines. Please Re-Post for receiving the answers on the other Questions.

Q1

Answer)

Bar charts and activity network diagrams provide different views of a project's schedule and tasks.

A bar chart is a char that is easy to view, read and understand and thus data can be easily represented and compared to each other. Thus, project related information and specific information such as profits, productivity, and others are listed in a bar chart to provide the project team or any other concerned team or party to provide the progress and other related information about the project from the individual activities of a bar chart.

An activity network diagram is a diagram consisting of the sequential relationships of activities using the nodes and arrows and thus connecting the different activities in a project or tasks and thus is used mainly in the identification of a project’s critical path. Thus, the expected completion time of the project is easier to find. The activity network diagram is used to determines also the Critical path, Most Likely Time, Optimistic Time, Pessimistic Time and Expected Time.

Thus we see that a bar chart is used for a different purpose while activity network diagrams are used for a different purpose.