The possible paths in the AON diagram and their corresponding durations as follo

ID: 374298 • Letter: T

Question

The possible paths in the AON diagram and their corresponding durations as follows are :

A1 – A2-A3-A4-A8 = 3 + 4 + 2+ 5 + 3 DAYS = 17 DAYS

A1 – A2 -A3 -A6- A7- A8 = 3 + 4 + 2 + 2+2+ 3 = 16 DAYS

A1-A2-A5-A7-A8 = 3 +4 +7 +2+3 = 19 DAYS

Out of above , A1-A2-A5-A7-A8 has the longest duration and hence forms the critical path . The duration of the criticalpath is same as project completion time .

Therefore, earliest completion time of the project = 19 days

EARLIEST COMPLETION TIME OF THE PROJECT = 19 DAYS

EARLIEST COMPLETION TIME OF THE PROJECT = 19 DAYS

Explanation / Answer

019-3 3. Consider the AON graph of a project shown in Figure 19.18. Figure 19.18 A3 A6 ( A2 A7 A5 The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A, through Ag respectively. What is the earliest completion time of the project?

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote