The correct answer is it increases network sensitivity as reduction in duration would mean that we are cutting all the buffers and hence a slight change alters the entire project system.

It is not true that it is always more expensive, it is many a times cheaper as well as duration decreases resulting in the decrease in cost as well. Option E is also wrong as it is not necessary to crash all activities. Also, it cannot be considered for all projects as some projects require that the schedule should not be altered.

Explanation / Answer

Question 2 (5 points) Reducing project duration O A) Should be considered for all rojects O B) Can only be done when resources are not constrained. C) Is always more expensive )Tends to increase network sensitivity. E) Involves crashing ali activities to their crash point save uestion 3 (5 points) contractor finshed s bridge scross a lake 1a menths eery ant rece