Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The new director of special events at a large university has decided to complete

ID: 371531 • Letter: T

Question

The new director of special events at a large university has decided to completely revamp graduation ceremonies. Toward that end, a PERT chart of the major activities has been developed. The chart has five paths with expected completion times and variances as shown in the table. Graduation day is 16 weeks from now.

Use Table B and Table B1.


Assuming the project begins now, what is the probability that the project will be completed before: (Round your z-value to 2 decimal places and all intermediate probabilities to 4 decimal places. Round your final answers to 4 decimal places.)
  

a. Graduation time?

Probability for graduation time             

b. The end of week 15?

Probability at the end of week 15             

c. The end of week 13?

Probability at the end of week 13            

Path Expected Duration
(weeks) Variance A 10 1.21 B 8 2.00 C 12 1.00 D 15 2.89 E 14 1.44

Explanation / Answer

Path

Expected Duration

Variance

(weeks)

A

10

1.21

B

8

2.00

C

12

1.00

D

15

2.89

E

14

1.44

Steps

There are five paths (not activities). The path which takes the longest time is the critical path. Here it is path D with 15 weeks. This is the mean completion time of the project.

Mean completion time of the project =15 weeks

Standard deviation of the project= (variance ) =(2.89 ) = 1.7

Find z ( the standardized deviation of the project from mean) and find the corresponding probability(area under curve) for Z using table

a.

Probability that the project will be completed before graduation-16 weeks

Z=Specified time Path mean /Path standard deviation =16-15/1.7 =0.5882

From z table (standard normal distribution table , we find the probability for the Z value as 0.5882

0.719 or 71.9%

B.

Probability that the project will be completed before 15 weeks

Z=Specified time Path mean /Path standard deviation =15-15/1.7 =0.5000

From z table (standard normal distribution table , we find the probability for the Z value as 0.5000

50%

C.   

Probability that the project will be completed before 13 weeks

z =Specified time Path mean /Path standard deviation =13-15/1.7 =-1.1764

From z table (standard normal distribution table, we find the probability for the Z value as 0.1210

12.1%

Path

Expected Duration

Variance

(weeks)

A

10

1.21

B

8

2.00

C

12

1.00

D

15

2.89

E

14

1.44

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote