Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The folowing is a table of activities associated with a project at Rafay Ishfaqg

ID: 368705 • Letter: T

Question

The folowing is a table of activities associated with a project at Rafay Ishfaqg's scftware firm in Chicago, their durations, what activies each musi precede and the orash cost to reducs duration per week Activity Duration (weeks) Precedes Crash Cost/Week A (stant) B, C $120 F (and) Suppose that Relay is only given 7 woeks (instead of 10) to complete the project By how many wooks shoud each activity be crashed in order to moet the deadine? Assume that you can crash an woeks durebion Each Activity Should be Reduced BY Activity 3 woek[s) Enter your answer in the answer box and then click Check Answer

Explanation / Answer

There is another option:

Task Pre Duration ES EF Critical LS LF Slack A NA 2 0 2 yes 0 2 0 B A 2 2 4 3 5 1 C A 5 2 7 Yes 2 7 0 E B 2 4 6 5 7 1 F C,E 3 7 10 Yes 7 10 0
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote