Question Help * Problem 15.16 The following 5 overhaul jobs are waiting to be pr

ID: 368443 • Letter: Q

Question

Question Help * Problem 15.16 The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places) Job CR Due Date 214 223 217 219 216 Durton (days) Job 103 205 309 412 517 103 15 Assume that all jobs arrived on day 180, today's date is 200 Enter your answer in the answer box and then click Check Answer. Check Answer Clear All remaining

Explanation / Answer

Job

Time Since Order Arrived (days ago)

Processing Time (days)

Today's Date

Due Date

Due Date (days from now)

Slacking time

Critical ratio

103

20

10

200

214

14

4

1.4

205

20

7

200

223

23

16

3.3

309

20

11

200

217

17

6

1.5

412

20

5

200

219

19

14

3.8

517

20

15

200

216

16

1

1.1

Due date-Today

Due/Process time

Job

Time Since Order Arrived (days ago)

Processing Time (days)

Today's Date

Due Date

Due Date (days from now)

Slacking time

Critical ratio

103

20

10

200

214

14

4

1.4

205

20

7

200

223

23

16

3.3

309

20

11

200

217

17

6

1.5

412

20

5

200

219

19

14

3.8

517

20

15

200

216

16

1

1.1

Due date-Today