Question Help * Problem 15.16 The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places) Job CR Due Date 214 223 217 219 216 Durton (days) Job 103 205 309 412 517 103 15 Assume that all jobs arrived on day 180, today's date is 200 Enter your answer in the answer box and then click Check Answer. Check Answer Clear All remainingExplanation / Answer
Job
Time Since Order Arrived (days ago)
Processing Time (days)
Today's Date
Due Date
Due Date (days from now)
Slacking time
Critical ratio
103
20
10
200
214
14
4
1.4
205
20
7
200
223
23
16
3.3
309
20
11
200
217
17
6
1.5
412
20
5
200
219
19
14
3.8
517
20
15
200
216
16
1
1.1
Due date-Today
Due/Process time
Job
Time Since Order Arrived (days ago)
Processing Time (days)
Today's Date
Due Date
Due Date (days from now)
Slacking time
Critical ratio
103
20
10
200
214
14
4
1.4
205
20
7
200
223
23
16
3.3
309
20
11
200
217
17
6
1.5
412
20
5
200
219
19
14
3.8
517
20
15
200
216
16
1
1.1
Due date-Today
Due/Process time
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.