Four existing assembly lines have the flexibility to handle two products, but a

ID: 366410 • Letter: F

Question

Four existing assembly lines have the flexibility to handle two products, but a huge jump in budgeted demand requires adding additional lines.

Operations are scheduled for 350 days/year with two shifts of 10 hours each per day. In order to ensure they can react to rush or large orders, a 15% capacity cushion is desired. How many additional assembly lines are needed to deal with the following forecast:

Model A. Model B

   Annual Demand     40,000       60,000

   Set-up Time/ Batch   4 hrs          6 hrs

   Run Time per unit   30 min         1 hr

   Batch Size                2,000         3,000

Explanation / Answer

The capacity requirement for both the models is calculated as shown below:

Model A

Model B

Annual Demand

A

40,000

60,000

Std. Processing time (hours)

tp

30/60 = 0.5

1

Avg. Lot Size

L

2000

3000

Std. Setup Time per lot (hours)

ts

4

6

Total Processing time (hours)

B = (A x tp)

20000

60000

Total Setup time (hours)

C = (A/L) x (ts)

80

120

Total Time required (hours)

D = B + C

20080

60120

Total Time req. considering cushion (hours)

(Cushion = 15%)

E = D + 0.15D

23092

69138

Total time production time required

T

23092 + 69138

= 92230

Time available per line (hours/year)

TA = 350 days x 2 shifts x 10 hours/shift

7000

Number of lines required

N = T/TA

13.18

Actual number of machines required

14

Current available number of lines

4

Additional number of lines required

14 - 4 = 10

Additional assembly lines required = 10 lines

Model A

Model B

Annual Demand

A

40,000

60,000

Std. Processing time (hours)

tp

30/60 = 0.5

1

Avg. Lot Size

L

2000

3000

Std. Setup Time per lot (hours)

ts

4

6

Total Processing time (hours)

B = (A x tp)

20000

60000

Total Setup time (hours)

C = (A/L) x (ts)

80

120

Total Time required (hours)

D = B + C

20080

60120

Total Time req. considering cushion (hours)

(Cushion = 15%)

E = D + 0.15D

23092

69138

Total time production time required

T

23092 + 69138

= 92230

Time available per line (hours/year)

TA = 350 days x 2 shifts x 10 hours/shift

7000

Number of lines required

N = T/TA

13.18

Actual number of machines required

14

Current available number of lines

4

Additional number of lines required

14 - 4 = 10

Hire Me For All Your Tutoring Needs