Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Four existing assembly lines have the flexibility to handle two products, but a

ID: 366406 • Letter: F

Question

Four existing assembly lines have the flexibility to handle two products, but a huge jump in budgeted demand requires adding additional lines. Operations are scheduled for 350 days/year with two shifts of 10 hours each per day. In order to ensure they can react to rush or large orders, a 12% capacity cushion is desired. How many additional assembly lines are needed to deal with the following forecast: Model A Model B Annual Demand 40,000 60,000 Set-up Time/ Batch 4 hrs 6 hrs Run Time per unit 1 hr 30 min Batch Size 2,000 3,000

Explanation / Answer

Capacity of a line = no. of days x available hours per day

= 350x 10x2 =7000 hours per annum

As we need a buffer of 12% the effective available time

= 7000x(1-0.12) = 6160 p.a.

Time needed for item A

No. of batches = annual demand/ batch size = 40000/2000 =20

Time consumed in a batch production =2000x1.5 =3000 hrs

Total production time =20x3000=60000

Total set up time =20x4 =80

Total time for A =60080

Time needed for item B

No. Of batches = 60000/3000 =20

Time consumed in a batch production

= 1.5x3000 = 4500

Total time of production

= 4500x 20 =90000

Set up time = 6x20=120

Total time for item B

90000+120=90120

Total time requirement for production of A and B

60080+90120 =150200

Number of lines needed = 150200/6160 = 24.38 = 25

Therefore we need 21 more lines to meet the demand.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote