You are the project manager for a construction company. You are currently est estimate that there wiring will take approximately 250 hours. Which of the following estimating techniques did you apply in your analysis? imating how long it will take to perform the electrical wiring of the building. You are about s,000 meters of wiring required. You also estimate that your project team can wire 20 meters/hour 0 1) Analogous estimating O 2) Top-down estimating O 3) Parametric estimating 4) Bottom-up estimating Question 6 o / 1 point approximation of the costs of the resources needed to complete each schedule activity. All of the following are tools techniques you can use in this process EXCEPT: 1) Cost aggregation O2) Analogous estimation, bottom-up estimation, parametric estimation 3) Determine resou cost rate, cost of qualityExplanation / Answer
The correct option is Option C
Parametric estimating.
This estimation includes the estimation of time taken by a task and unit required to complete the activity.
Your second question is incomplete. 4th option is missing.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.