18. The reorder point will be equal to which of the following: a. The EOQ b. Exp

ID: 355784 • Letter: 1

Question

18. The reorder point will be equal to which of the following: a. The EOQ b. Expected usage during lead time c. Safety stock d. The service level e. The EOQ plus safety stock 19. A Chevrolet manufacturing plant and McDonalds would both be considered a: a. Process layout b. Fixed Position Layout c. Product Layout d. Job Shop Layout e. Both A and D Which of these would generally have independent demand: subassemblies, component parts, finished goods? 20. a. Subassemblies b. Component parts c. Finished goods d. All of these e. None of these 21 In a project network the critical path is the sequence of activities which has: a. The most activities b. The longest time c. The most nodes d. The most events e. The greatest variance 2 The time between the issuance of a replenishment order and the receipt of stock is a stock time b. in-process time c. work content time d. lead time e none of the above

Explanation / Answer

18) The reorder point will be equal to which of the following:

Answer: Option (B) - Expected usage during lead time

19) A Chevrolet manufacturing plant and McDonalds would both be considered a:

Answer: Option (E) - Both A and D

20) Which of these would generally have independent demand?

Answer: Option (C) - Finished goods

21) In a project network the critical path is the sequence of activities which has:

Answer: Option (B) - The longest time

22) The time between the issuance of a replenishment order and the receipt of stock is

Answer: Option (D) - Lead time