PLEASE ANSWER PROBLEM 11!!! 2. Using the network above and the additional inform
ID: 350630 • Letter: P
Question
PLEASE ANSWER PROBLEM 11!!!
2. Using the network above and the additional information below, find: (a) The crash cost per day (b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost. Assume partial crashing is allowed. Crash Time Activity (days(total) Crashed Cost Normal Time (days) Normal Cost S300 325 4 550 150 11. Reconsider Problem 2, assuming a fixed overhead cost of S30 per day but no project deadline. What is the least-cost crash program? What if the overhead cost was $40? What if it was $60Explanation / Answer
11.
From Part 2
We can see the critical path of Project is B-C-D with duration = 15 days
Project Duration without crashing = 15 days
Total Cost without crashing = Cost of all activities + Overhead cost * Project Duration = Sum of Normal cost of alll activities + 15*30 = 1100+450 = 1550
Find Crash cost per day of different activities
We can see lowest cost per day is for Activities D and we can reduce it by 3 days with additional cost of 250
Post Crashing activity by 3 days
Project Duration = 15-3 = 12
Now Project Cost = Cost of all activities + Overhead cost * Project Duration + Crash cost = 1100 + 30*12 +250 = 1100 +360+250 = 1710 which is higher than original duration cost
so for least -cost crash program , Crash cost < (Reduce in project Duration due to crash)* Overhead cost
so by Reducing D by 3 days
Crash cost = 250
with Overhead cost = 30
Reduction in project cost due to crashing = 30*3 = 90
However additional cost of 250 was taken so net buget will increase by 250-90 = 160
with Overhead cost = 40
Net budget change = 250-120 = 130 increase in budget
So cost of project = 1550+130 = 1680
Overhead cost = 60
Net Budget change = 250 - 180 = 70
So cost of project = 1550+70=1630
so in all the cases the crashing will not lead to any reduction in budget in case of crashing
In all the above case, Least-cost project = 1550
Activities Crashed Time Crashed Cost Crash Cost Per Day A 3 500 166.7 B 1 325 325.0 C 4 550 137.5 D 3 250 83.3Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.