ST MISSOURI ERSITY 1873 7-740 Mfg Resource Analys 20787 tudies Spring 2018 IM417-740 20 787 Week 8 > Mderm Exam Question 23 Not yet answered make a MRP for this product All lead times are one week, and the quantities required are shown in the aiat aa st4o product tree. The master production schedule calls for 500 As to be available in woek 5, and 300 As to Given the followving product tree, explode, offset and determine the gross and net requiremants,and Marked out of 4.00 be available in week 4. There are 60 Bs 250 Cs, and 200 Ds as projected available at beginning The Y Flog quesion policy for projected available and scheduled recoipt is first-come-first use In the MRP what is Planned Order Release for Part C in week 2? Select one A 350 B 450 C 550 D 650 E None of them

Explanation / Answer

In week 4 300 As are required.

For each A we need 3 C's.

hence for 300 A, we need 900 C.

lead time of all is one week. for completion of A by week5 we need all the raw materials of A by start of week 4 or end of week 3.

similarly to complete order of 300 A by week 4 we need to have C by end of week 2.

Hence 900 C is to be released by week 2. but we already have 250 C in stock.

Hence, 900 - 250 = 650 C is required.

Ans: option D.