You must show your working. No credit will be given if caleulation is not shown
ID: 344675 • Letter: Y
Question
You must show your working. No credit will be given if caleulation is not shown Section A: 2 points each 1. A production line is designed to produ 1000 minutes a day. The manufacture of each doll)consisting o desired cycle time for this assembly is a. one-half minute b. two minutes c. 62.5 minutes d. 8,000 minutes arket demand 500 dolls per day. Dhe factory operates f es 16 minutes. The annot be determined 2. Define productivity mathematically? Produetuty o utut dvioua by mpu 3. Which of the following is not a requirement of the structure of a linear programming model formulation? (2 points) a. constraints b. decision variables c. probabilities d. objective function 4. Define Operations Management 5. Specify three differences between a product and a service.Explanation / Answer
Section A
1. cycle time = Time / quantity required = 1000/500 =2 min.
2. It is output per unit of input.
3. c
4. It is the management of business practices that lead to conversion of input ( raw material) into output (finished products) with utmost efifciency to maximize the profitability for the organization.
5. A service is intangible unlike the product which can be felt and have physical dimensions. A service is time dependant and perishable and can't be stored like a product. A service needs some degree of interaction betwee the server and the availing person, while it is not true with product.
6.b
7c
8
MFP = 1124x100 / 12735+21041+8992 = 112400 / 42768 =2.628