Activity Normal Time Crash Time Cost per day to crash A 6 6 --- B 10 8 $100 C 5
ID: 3437891 • Letter: A
Question
Activity
Normal Time
Crash Time
Cost per day
to crash
A
6
6
---
B
10
8
$100
C
5
4
$300
D
4
1
$700
E
9
7
$500
F
2
1
$650
Determine which activities should be crashed to shorten the project by 1 day
Determine which activities should be crashed to shorten the project by 2 days.
Crash activity B by 1 day and Activity C by 1 day.
Crash activity E by 2 days.
Crash activity C by 1 day and activity E by 1 day.
Crash activity B by 2 days.
Activity
Normal Time
Crash Time
Cost per day
to crash
A
6
6
---
B
10
8
$100
C
5
4
$300
D
4
1
$700
E
9
7
$500
F
2
1
$650
StartExplanation / Answer
Under normal times the two paths that can be followed are:
ABF = 15 (under normal times)
CDEF = 13 (under normal times)
To shorten the project by one day, any of the activities could be crashed except for A, since the maximum reduction in A possible is zero.
It would be wisest to shorten B as it is the least expensive to crash.
For the next question we determine each of the options:
Hope this helps.
Activity NT CC Cost Max Redn A 6 6 --- 0 B 10 8 $100 2 C 5 4 $300 1 D 4 1 $700 3 E 9 7 $500 2 F 2 1 $650 1Related Questions