As it relates to an activity network diagram (PERT chart), which of the follow statements is False or LEAST true?
Length of time is important.
Tasks are listed.
The critical path are the tasks that are the most difficulty to accomplish.
From start to finish, there may be multiple paths.
None of the above.
1Length of time is important.
2Tasks are listed.
3The critical path are the tasks that are the most difficulty to accomplish.
4From start to finish, there may be multiple paths.
5None of the above.
Explanation / Answer
Option 3 is false as the critical path is the longest possible path from start to finish which represents the total time allotted and the delays beyond that indiacate the delay in project.