As it relates to an activity network diagram (PERT chart), which of the follow s

ID: 339312 • Letter: A

Question

As it relates to an activity network diagram (PERT chart), which of the follow statements is False or LEAST true?

Length of time is important.

Tasks are listed.

The critical path are the tasks that are the most difficulty to accomplish.

From start to finish, there may be multiple paths.

None of the above.

1

Length of time is important.

2

Tasks are listed.

3

The critical path are the tasks that are the most difficulty to accomplish.

4

From start to finish, there may be multiple paths.

5

None of the above.

Explanation / Answer

Option 3 is false as the critical path is the longest possible path from start to finish which represents the total time allotted and the delays beyond that indiacate the delay in project.