Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

A well-written report would contain the following elements: required to develop

ID: 335218 • Letter: A

Question

A well-written report would contain the following elements:

required to develop a Risk management plan or contingency plan to manage risk effectively in an organization. You may choose to work on any one of the following areas:

a.         Hospitals

b.         Real Estate

c.         Chemical Industry

d.         Manufacturing Unit

e.         Energy plant

f.          Enterprise

The Risk management plan should cover in detail

Risk Identification, Risk Analysis, Risk Response Planning, Risk monitoring and control.

Explanation / Answer

Company example into Energy/ Oil and Gas- Gas Authority of India Ltd.:

Consequence analysis takes the following aspects into account:

Risk Assessment:

The risk matrix is a widely accepted and standardized method of quantitative risk assessment and is preferred over purely quantitative methods, given its inherent limitations to define a risk event with certainty using order of magnitude data (risk ranking = severity/consequence factor X likelihood/probability factor).

Risk Response Chart:

Consequence

Ranking

Criterion Definition

Response

Catastrophic

5

A) Multiple fatalities/Permanent total disability to more than 50

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) Severe violations of national limits for environmental emission. More than 5 years for natural recovery

Installation of hydrocarbon detectors

C) Net negative financial impact of >10 crores

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D) Long term impact on ecologically sensitive areas

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E) National stakeholder concern and media coverage

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

Major

4

A) Single fatality/permanent total disability to one or more persons

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) Major violations of national limits for environmental emissions. 2-5 years for natural recovery

Installation of hydrocarbon detectors

C) Net negative financial impact of 5 -10 crores

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D) Significant impact on endangered and threatened floral and
faunal species

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E) Loss of corporate image and reputation

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

   Moderate

3

A) Short term hospitalization and rehabilitation leading to recovery

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) Short term violations of national limits for environmental

Installation of hydrocarbon detectors

C) Net negative financial impact of 1-5 crores

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D)Short term impact on protected natural habitats

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E)State wide media coverage

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

Minor

2

A) Medical treatment injuries

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) 1 year for natural recovery

Installation of hydrocarbon detectors

C) Net negative financial impact of 0.5 – 1 crore

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D) Temporary and mitigatable environmental impacts

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E)Local stakeholder concern and public attention

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

Insignificant

1

A) First Aid treatment with no Lost Time Incidents (LTIs)

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) Natural recovery < 1year

Installation of hydrocarbon detectors

C) Net negative financial impact of <0.5 crores.

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D) No significant impact on environmental components

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E) No media coverage

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

Risk Scoring Matrix:

Likelihood ?

Frequent

Probable

Remote

Not Likely

Improbable

?

5

4

3

2

1

Consequence

Catastrophic

5

25

20

15

10

5

Major

4

20

16

12

8

4

Moderate

3

15

12

9

6

3

Minor

2

10

8

6

4

2

Insignificant

1

5

4

3

2

1

Risk Criteria and Action Requirements:

Risk Significance

Criteria Definition and Action Requirements

High (16 - 25)

“Risk requires attention” – Project HSE Management need to ensure that

necessary mitigation are adopted to ensure that possible risk remains within

acceptable limits

Medium (10 – 15)

“Risk is tolerable” – Project HSE Management needs to adopt necessary

measures to prevent any change/modification of existing risk controls and

ensure implementation of all practicable controls.

Low (5 – 9)

“Risk is acceptable” – Project related risks are managed by well-established

controls and routine processes/procedures. Implementation of additional

controls can be considered.

Very Low (1 – 4)

“Risk is acceptable” – All risks are managed by well-established controls and

  routine processes/procedures. Additional risk controls need not to be

considered

Consequence

Ranking

Criterion Definition

Response

Catastrophic

5

A) Multiple fatalities/Permanent total disability to more than 50

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) Severe violations of national limits for environmental emission. More than 5 years for natural recovery

Installation of hydrocarbon detectors

C) Net negative financial impact of >10 crores

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D) Long term impact on ecologically sensitive areas

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E) National stakeholder concern and media coverage

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

Major

4

A) Single fatality/permanent total disability to one or more persons

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) Major violations of national limits for environmental emissions. 2-5 years for natural recovery

Installation of hydrocarbon detectors

C) Net negative financial impact of 5 -10 crores

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D) Significant impact on endangered and threatened floral and
faunal species

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E) Loss of corporate image and reputation

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

   Moderate

3

A) Short term hospitalization and rehabilitation leading to recovery

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) Short term violations of national limits for environmental

Installation of hydrocarbon detectors

C) Net negative financial impact of 1-5 crores

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D)Short term impact on protected natural habitats

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E)State wide media coverage

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

Minor

2

A) Medical treatment injuries

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) 1 year for natural recovery

Installation of hydrocarbon detectors

C) Net negative financial impact of 0.5 – 1 crore

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D) Temporary and mitigatable environmental impacts

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E)Local stakeholder concern and public attention

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

Insignificant

1

A) First Aid treatment with no Lost Time Incidents (LTIs)

Marking of hazardous zone (500 meters) around the well site and monitoring of human movements in the zone.

B) Natural recovery < 1year

Installation of hydrocarbon detectors

C) Net negative financial impact of <0.5 crores.

Close monitoring of drilling activity be done to check for signs of increasing pressure, like shallow gas formations.

D) No significant impact on environmental components

Periodic monitoring and preventive maintenance be undertaken for primary and secondary barriers installed for blow out prevention, including third party inspection and testing

E) No media coverage

An appropriate Emergency Response Plan be formulated and implemented by GAIL.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote