The following jobs are waiting to be processed at Rick? Solano\'s machine center

ID: 335129 • Letter: T

Question

The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241.

(Job) (Date Job Received) (Due Date Duration (days))

BR-02 225 270 25

CX-01 230 320 35

DE-06 235 360 40

RG-05 231 310 30

SY-11 228 300 15

Using the SPT? (shortest processing? time) decision rule for sequencing the? jobs, the order is? (to resolve a? tie, use the order in which the jobs were? received):

The average tardiness? (job lateness) for the sequence developed using the SPT rule? =

The percentage utilization for the sequence developed using the SPT rule?=

The average completion time for the sequence developed using the SPT rule?=

The average number of jobs in the system for the sequence developed using the SPT rule? =

Explanation / Answer

The SPT rule in the following:-

Average completion time = total flow time/ no. Of jobs

= 1149 / 5

= 229.8 days

Utilisation = total processing time / total flow time

= 25 / 1149

=. 0.02175 %

Average no. of jobs = total flow time / total processing time

= 1149 / 25

=. 45.96 Jobs

Average jobs delay = total delays days / no. of jobs

= 145/ 5

= 29 days

Job sequence processing time Flow time Due date Delays BR 02 225 270 25 CX 01 230 320 35 DE 06 235 360 40 RG 05 231 310 30 SY 11 228 300 15 25
1149 1560 145