The following jobs are waiting to be processed at Rick? Solano\'s machine center
ID: 335125 • Letter: T
Question
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241.
(Job) (Date Job Received) (Due Date Duration (days))
BR-02 225 270 25
CX-01 230 320 35
DE-06 235 360 40
RG-05 231 310 30
SY-11 228 300 15
Using the EDD? (earliest due? date) decision rule for sequencing the? jobs, the order is? (to resolve a? tie, use the order in which the jobs were? received):
The average tardiness? (job lateness) for the sequence developed using the EDD rule? =
The percentage utilization for the sequence developed using the EDD rule? =
The average completion time for the sequence developed using the EDD rule? =
The average number of jobs in the system for the sequence developed using the EDD rule? =
Explanation / Answer
The Earliest Due Date rule is used to minimize the maximum lateness of schedule. According to EDD rule, the jobs are sequenced from earliest to latest due date of job. The sequence of EDD is as follows:
1
2
3
4
5
6 = 5+4
7
8 = 7 - (240 day)
9 = Maximum (0, (6 – 8))
Sequence
Job
Date Received
Processing time
Work Begins
Flow Time
Job Due date
Starting from day 241
Job Lateness
(Tardiness)
pi
di
1
BR-02
225
25
0
0+25
= 25
270
270-240
= 30
=max(0, (25-30))
= max(0, -5)
= 0
2
SY-11
228
15
25
40
300
60
0
3
RG-05
231
30
40
70
310
70
0
4
CX-01
230
35
70
105
320
80
25
5
DE-06
235
40
105
145
360
120
25
145
385
50
Total Processing time = 145 days
Total flow time for 5 jobs = 385 days
Total tardiness = 50 days
Average tardiness = total tardiness/number of jobs in sequence = 50/5 = 10 days
Percentage Utilization = total processing time/total flow time x 100
Percentage Utilization = 145/385 x 100 = 37.66%
Average completion time = Total Flow time/number of jobs in sequence = 385/5 = 77 days
Average number of jobs in system = Sum of total flow time/Total processing time = 385/145 = 2.65
For EDD:
Average tardiness = 10 days
Percentage Utilization = 37.66%
Average completion time = 77 days
Average number of jobs in system = 2.65 jobs
1
2
3
4
5
6 = 5+4
7
8 = 7 - (240 day)
9 = Maximum (0, (6 – 8))
Sequence
Job
Date Received
Processing time
Work Begins
Flow Time
Job Due date
Starting from day 241
Job Lateness
(Tardiness)
pi
di
1
BR-02
225
25
0
0+25
= 25
270
270-240
= 30
=max(0, (25-30))
= max(0, -5)
= 0
2
SY-11
228
15
25
40
300
60
0
3
RG-05
231
30
40
70
310
70
0
4
CX-01
230
35
70
105
320
80
25
5
DE-06
235
40
105
145
360
120
25
145
385
50