The following information is known about a project to upgrade a? point-of-sale s

ID: 333282 • Letter: T

Question

The following information is known about a project to upgrade a? point-of-sale system at Kids and Tots? Apparel:

????????????????????????????????????????????????????????????????????????????????????????????????????????????????????????  

Activity

?(dayday?s)

Immediate? Predecessor(s)

A

88

B

11

A

C

55

A

D

55

?B, C

E

55

D

F

22

E

G

88

E

The critical path is path is A-C-D-E-G and the project duration is 31 days.

c. Calculate the slack for each activity.

?(Enter your responses as integers?.)

Slack

?(day?s)

Activity

A

nothing

B

nothing

C

nothing

D

nothing

E

nothing

F

nothing

G

nothing

Activity

Activity Time

?(dayday?s)

Immediate? Predecessor(s)

A

88

B

11

A

C

55

A

D

55

?B, C

E

55

D

F

22

E

G

88

E

Explanation / Answer

The precedence diagram of activities as follows /:

                                                                                                                  A

                                                      B

                                                    C

                                                                                                                    D

                                                                                                                    E

                                                                                                      F

                 G

The possible paths and their corresponding durations as follows :

Path A-B-D-E-F = 88 + 11 + 55 + 55 + 22 = 231

Path A-B-D-E-G = 88 + 11 + 55 + 55 + 88 = 297

A-C-D-E-F = 88 + 55 + 55 + 55 + 22 = 275

Path A-C-D-E-G = 88 +55+ 55 + 55 + 88 = 341

Since A-C-D-E-G has the longest duration, it forms the critical path. Therefore , project duration = Duration of critical oath = 341

Slack for each activity is difference between Early Start time and Late start time or Difference between Early finish time and Late Finish time .

It is to be noted that all activities lying on critical path will have ZERO Slack.

Therefore , Slack for activities A, C, D,E and G will have ZERO sack

Slack for activity F = Duration of   A-C-D-E-G – Duration A-C-D-E-F = 341 – 275 = 66

Slack for activity B = Duration A-C-D-E-G- duration A-B-D-E-G = 341 – 297 = 44

ACTIVITY

SLACK ( DAYS)

A

0

B

44

C

0

D

0

E

0

F

66

G

0