Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following information is for the standard and actual costs for the Carson Pa

ID: 2464999 • Letter: T

Question

The following information is for the standard and actual costs for the Carson Palmer Corporation.

Standard Costs:

Budgeted units of production - 16,000 (80% of capacity)

Standard labor hours per unit – 4 Standard labor rate $26 per hour

Standard material per unit - 8 lbs.

Standard material cost - $ 12 per lb.

Budgeted fixed overhead $640,000

Standard variable overhead rate - $15 per labor hour.

Fixed overhead rate is based on budgeted labor hours at 80% capacity.

Actual Cost:

Actual production - 16,500 units

Actual fixed overhead - $640,000

Actual variable overhead - $1,000,000

Actual labor - 65,000 hours, total labor costs $1,700,000

Actual material purchased and used - 130,000 lbs, total material cost $1,600,000

Actual variable overhead - $1,000,000

1) Find The total Factory Overhead Controllable Variance.

Explanation / Answer

Total Factory Overhead Controllable variance =

= Actual variable overhead - Variable expenses for standard hours allowed

= 1,000,000 - 960,000

= 40,000 (U)

Working:

1. Variable expensed for standard hour = Total Standard Production * Standard Labour hour per unit * variable overhead rate

= 16000 * 4 *15 = 960,000