Based on the following PERT chart: A(6) Start End F(5) How many tasks are there

ID: 331689 • Letter: B

Question

Based on the following PERT chart: A(6) Start End F(5) How many tasks are there for the project? What is the total task time for the project? G(4) H(5) What is the critical time for the project? Based solely on the critical time and average time, what is the lowest finishing time for the project if the project is being completed by two processors? Based solely on the critical time and average time, what is the lowest finishing time for the project if the project is being completed by three processors?

Explanation / Answer

Total number of task = 8

Total task time for the project = 6+11+ 8 = 26

average time for the project = 24+26/2 = 25

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote