Question 5 John is the project leader for his division’s move to a new building.

ID: 331571 • Letter: Q

Question

Question 5 John is the project leader for his division’s move to a new building. During the execution phase of the project, several of the stakeholders begin to request new features and changes to the original requirements. What should John do? Choose from the following answers?

Refuse to make any changes to the plan once the execution phase begins.

Be responsive to stakeholder needs and adopt the changes wherever possible.

Accept or reject changes based on project goals.

Only accept change requests that will not increase the cost of the project.

Explanation / Answer

The correct answer is: Refuse to make any changes to the plan once the execution phase begins.

Once the plan is confirmed and the execution starts the changes should not be made. This can deviate from the goal of the project and demand new a plan and resources to incorporate them.