A software project requires 11 components to be completed within the next three
ID: 3301607 • Letter: A
Question
A software project requires 11 components to be completed within the next three months. Each component is produced by a programming team that operates independently of the other team has a 50% change of finishing on time within the next three months. Is there a 50% change that the project will be finished on time? Choose the correct answer below. A. Yes, there is a 50% chance that the project will be finished on time. B. No, the probability is (0.5^11), which is less than 50%. C. No, the probability is 0.5/11, which is less than 50%. D. No, the probability is 1 - (0.6)^11, which is greater than 50%.Explanation / Answer
Given there are 11 components to complete project within three months.
EAch component has probability of 0.50 to finish on time, all components are independent
The probability to complete whole project within 3 months of time = 0.5*0.5*...*0.5 = (0.5)11
(for 11components, since they are independent and all has to complete to finish the project )
B) No, the probability is 0.511, which is less than 50%
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.