A company conduct a work sampling study to estimates the proportion of time thei
ID: 329946 • Letter: A
Question
A company conduct a work sampling study to estimates the proportion of time their workers on idle during the process. The table below shows the data.
Times busy
Times idle
Total observations
(a) What is the estimated percentage of idle time?(answer 0.238
(b) Based on the initial results, approximately how many more observations would you require estimating the actual percentage of idle time to within 5% with a confidence of 98%? (Ans. 352 more observations)
Using the information in the following grid, determine if the department locations shown are appropriate. If not, modify the locations so that the conditions are satisfied
Observation PeriodTimes busy
Times idle
Total observations
Monday 6 1 7 Tuesday 5 2 7 Wednesday 7 0 7 Thursday 9 2 11 Friday 5 5 10 Total 32 10 42Explanation / Answer
(a) Estimated percentage of idle time = 10/42 = 0.2380952 = 0.238
This is also called sample proportion, p = 0.238
(b) Required sample, n = (z/e)^2 * p * (1-p)
Here, z = No. of standard deviation for desired confidence level
For 98% confidence level, Z = 2.33
e = required error percentage limit = 5% = 0.05
p = 0.238
So, n = (2.33/0.05)^2 * 0.238 * (1 - 0.238)
=> n = 393.9338
=> n = 394
So, required sample size = 394.
So, additional observations required = 394 - 42 = 352
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.