Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Activity Percent Complete Budgeted Cost for Work Scheduled Budgeted Cost for Wor

ID: 328090 • Letter: A

Question

Activity

Percent Complete

Budgeted Cost for Work Scheduled

Budgeted Cost for Work Performed

Actual Cost for Work Performed

Cost Variance             = 4-5

Schedule Variance

= 4-3

Cost variance ($)= column 4 – column 5 ________________

Schedule variance ($) = column 4 – column 3 _______________

Time to complete = __________________________

Cost at completion = rate of spending x Total budget    column 5/column 4 x (    ) = __________

Cost to complete = (cost of completion) – ACWP= _________________________

Activity

Percent Complete

Budgeted Cost for Work Scheduled

Budgeted Cost for Work Performed

Actual Cost for Work Performed

Cost Variance             = 4-5

Schedule Variance

= 4-3

PERCENT-COMPLETION REPORT Time to Activity Date Started %Completed Complete AB AC AD DE* BF 100% 60% 100% not started 2/14 40% Note: Because of priorities, resources for activity DE will not be available until 3/14. Management estimates that this activity can be crashed from 3 weeks to 2 weeks at an additional cost of $3,000

Explanation / Answer

Activity % Complete Budgeted Cost for Work Scheduled Budgeted Cost for Work Performed Actual Cost for Work Performed Cost Variance Schedule Variance PV EV AC AB 100% $6,000 $6,000 $6,200 -$200 $0 AC 60% $20,000 $15,000 $12,500 $2,500 -$5,000 AD 100% $7,500 $7,500 $7,400 $100 $0 DE Not Started $10,500 $3,500 $0 $3,500 -$7,000 BF 40% $15,000 $2,000 $4,500 -$2,500 -$13,000

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote