Q6. CSRs at Sof-Optics had staggered breaks to ensure coverage of the phones at
ID: 327977 • Letter: Q
Question
Q6. CSRs at Sof-Optics had staggered breaks to ensure coverage of the phones at all times. True or False
Q7. Since most of Kristen's cookies use the same basic dough, one way Kristen could cut down her production time is to premix the dough and then postpone the addition of mix-ins until a customer places an order. True or False
Q8. Kristen and her roommate can increase cookie baking capacity by mixing enough dough at the same time to make two dozen cookies and by adding another tray to the oven to bake two dozen cookies at the same time. True or False
Q9. Cycle time is characteristic of a system while throughput time is associated with a particular job. True or False
Q10. Setup time depends on the number of items in a batch. True or False
Q11. In continuous processes, bottlenecks are shifting frequently. True or False
Explanation / Answer
Answer 6. True, it takes care of bottlenecks.
Answer 7. True, this is process otimization, provided the dough doesn't becomes stale.
Answer 8. True, provided the oven capacity is as per the plan.
Answer 9. False, The opposite is true
Answer 10. False. Setup time depends on the component type not qty.
Answer 11. False, Bottlenecks are constant, WIP may change