Activity M on a CPM network has predecessors N and R, and has successor S. M has
ID: 327862 • Letter: A
Question
Activity M on a CPM network has predecessors N and R, and has successor S. M has a duration of 5. N's late finish is 18, while R's is 20. S's late start is 14. Which of the following is true?
Activity M on a CPM network has predecessors N and R, and has successor S. M has a duration of 5. N's late finish is 18, while R's is 20. S's late start is 14. Which of the following is true? O None are true M is critical M has no slack but is not critical O The last start time of S is not possible. O S must be completed before NExplanation / Answer
The correct option is D. The last start time of S is not possible. All the other options mentioned are false.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.