Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

1. You can cut the cycle time of a process by doing all of the following EXCEPT:

ID: 325212 • Letter: 1

Question

1.

You can cut the cycle time of a process by doing all of the following EXCEPT:

Add resources

Shorten task time

Modify the existing process

Reduce customer demand for goods and services

2.

Activity utilization is calculated using which of the folllowing equations?

Time required / Time available

Direct labor hours / Total labor hours

Capacity required / Capacity available

(Total machine hours – Hours of machine down time) / Total hours

3. Another name for capacity is:

flow time

lead time

throughput time

throughput rate

Equipment spare parts and supplies are examples of which of the following types of inventories?

Raw materials inventories

Work-in-process inventories

Finished goods inventories

Maintenance, repair, and operating inventories

a.

Add resources

b.

Shorten task time

c.

Modify the existing process

d.

Reduce customer demand for goods and services

Explanation / Answer

Question 1). You can cut the cycle time of a process by doing all of the following EXCEPT:

Answer:- d) Reduce customer demand for goods and services

The reason being we can control the process at our end but we cannot reduce customer demand for goods and services. We can add resources, modify the existing process and shorten the task time to reduce the cycle time of a process.

Question 2). Activity utilization is calculated using which of the folllowing equations?

Answer:- a) Time required / Time available

By calculating the non-productive time we can easily calculate the activity utilization as per the above formula.

Question 3). Another name for capacity is:

Answer:- c) throughput time

Question 4). Equipment spare parts and supplies are examples of which of the following types of inventories?

Answer:- d) Maintenance, repair, and operating inventories