Activity Start A B C D E F G H End Time 0 3.68 1.37 3.69 6.15 4.65 6.87 4.68 2.6
ID: 3177097 • Letter: A
Question
Activity
Start
A
B
C
D
E
F
G
H
End
Time
0
3.68
1.37
3.69
6.15
4.65
6.87
4.68
2.65
0
a) The Project Completion time = __________(in 2 decimal places)
b) The Earliest Start time, ES, of Activity G = ________ (in 2 decimal places)
c) The Latest Finish time, LF, of Acitivity C = _________ (in 2 decimal places)
d) The critical activities are = __________ (ex. type in critical activities as ABCD, no comma, no space)
Activity
Start
A
B
C
D
E
F
G
H
End
Time
0
3.68
1.37
3.69
6.15
4.65
6.87
4.68
2.65
0
webapps assessment p c VITECEZ TV player Take Test S4AT x What is the Relation Question Completion Status: Start End Activity Start 3.68 3.69 4.65 6.87 a) The Project Completion timeExplanation / Answer
a) The Project Completion time = 19.35
b) The Earliest Start time, ES, of Activity G = 12.02
c) The Latest Finish time, LF, of Acitivity C = 9.83
d) The critical activities are = ACEGH
Activity time ES EF LS LF A 3.68 0 3.68 2.46 6.14 B 1.37 0 1.37 4.5 5.87 C 3.69 3.68 7.37 6.14 9.83 D 6.15 1.37 7.52 5.87 12.02 E 4.65 7.37 12.02 7.37 12.02 F 6.87 7.37 14.24 9.83 16.7 G 4.68 12.02 16.7 12.02 16.7 H 2.65 16.7 19.35 16.7 19.35Related Questions