Activity Based Costing: Vid-saver, Inc. has five activity cost pools and two pro

ID: 2476131 • Letter: A

Question

Activity Based Costing:

Vid-saver, Inc. has five activity cost pools and two products (a budget tape rewinder and a deluxe tape rewinder). Information is presented below:

                                                                                                         Cost Drivers by Product

Activity Cost Pool                  Cost Driver        Est. Overhead       Budget           Deluxe                                   

Ordering and Receiving         Orders                   $   110,000                  600                400

Machine Setup                        Setups                        297,000                  500                400

Machining                              Machine hours        1,000,000           150,000         100,000

Assembly                                Parts                        1,200,000        1,200,000         800,000

Inspection                               Inspections                 300,000                  550                450

Instructions

Compute the overhead cost per unit for each product. Production is 700,000 units of Budget and 200,000 units of Deluxe. Round your answer to the nearest cent. -Make sure to show how you got the answer.

Explanation / Answer

Ans) Vid-saver, Inc. Activity cost Tool Est.Overhead/Total Est.Activity Overhead Rate Overhead Rate Ordering & receiving $                                        110,000.00 1000 Orders $               110.00 Machine setup $                                        297,000.00 900 Setups $               330.00 Machining $                                    1,000,000.00 250000 Machine Hours $                   4.00 Assembly $                                    1,200,000.00 2000000 Parts $                   0.60 Inspection $                                        300,000.00 1000 Inspections $               300.00 Budget Activity cost Tool Cost Driver Rate Cost Assigned Ordering & receiving 600 $              110.00 $           66,000.00 Machine setup 500 $              330.00 $         165,000.00 Machining 150000 $                  4.00 $         600,000.00 Assembly 1200000 $                  0.60 $         720,000.00 Inspection 550 $              300.00 $         165,000.00 Total $     1,716,000.00 Production 700000 Cost Per unit $                      2.45 Per unit Deluxe Activity cost Tool Cost Driver Rate Cost Assigned Ordering & receiving 400 $              110.00 $           44,000.00 Machine setup 400 $              330.00 $         132,000.00 Machining 100000 $                  4.00 $         400,000.00 Assembly 800000 $                  0.60 $         480,000.00 Inspection 450 $              300.00 $         135,000.00 Total $     1,191,000.00 Production 200000 Cost Per unit $                      5.96 Per unit