Estimated durations are provided for four types of activity Analysis Production

ID: 3071680 • Letter: E

Question

Estimated durations are provided for four types of activity

Analysis

Production

Testing

Installation

Predecessors

None

50% of analysis

Production

Testing

Cost per week

$7000

$15000

$8000

$3000

Crews on hand

2

3

1

1

You can split jobs, but not across crews doing the same function. (So you could do a week of analysis on A1 with Analysis Crew 1, then have them do something else, and come back later and do the other 3 weeks on A1. But you can’t have Analysis Crew 1 and Analysis Crew 2 both work on the same project.) Production can’t start until 50% of Analysis is done and you can’t finish Production until Analysis is completely done. You can hire new crews and you have to hire staff prior to using them, because there is a four week training period to indoctrinate people into your company’s way of doing things (training is paid at the full rate for that type of crew).  So therefore, starting times may have to wait for your indoctrination program unless you have hired people ahead. For those periods after the four week orientation when you do not have work for them, you can rent them out to others at a loss of $2000 per week per crew. You can lay off crews after their work is done.

Create a Gantt chart scheduling the following jobs. If you miss the deadlines there is a pentalty of $50,000 per week. The revenues are collected at the end of the week the job is completed.

Job

Analysis

Production

Testing

Installation

Due by end of

Revenue

A1

4 weeks

7 weeks

3 weeks

2 weeks

Week 20

$200,000

A2

4 weeks

6 weeks

2 weeks

2 weeks

Week 20

$210,000

A3

6 weeks

9 weeks

3 weeks

3 weeks

Week 30

$250,000

A4

8 weeks

12 weeks

5 weeks

4 weeks

Week 40

$350,000

A5

8 weeks

14 weeks

6 weeks

5 weeks

Week 40

$400,000

Create a cash flow plan for maximum profit that shows:

Weeks each crew is to work, what they are to work on, cash flow

Analysis

Production

Testing

Installation

Predecessors

None

50% of analysis

Production

Testing

Cost per week

$7000

$15000

$8000

$3000

Crews on hand

2

3

1

1

Explanation / Answer

Answer:

Here we have to preapare a cash flow plan for maximum profit

Now we have prepare the revenue for project Cash flow

Salary for crew of analysis A1 18 7000 0 5000 126000 A2 12 7000 0 5000 84000 Salary for crew of production P1 30 15000 2 013000 424000 P2 23 15000 0 13000 345000 Salary for crew of testing T1 35 8000 13 6000 202000 Salary for crew of installation I1 39 3000 22 1000 95000 Total 1276000