The earthwork for a construction project could take 2 or 3 months with probabili
ID: 3042249 • Letter: T
Question
The earthwork for a construction project could take 2 or 3 months with probabilities of 0.4 and 0.6, respectively. Foundation work could take 3 or 4 months with probabilities of 0.7 and 0.3, respectively. Building the superstructure could take 5 or 7 months, with equal probabilities. Assume that the construction stages are statistically independent and must be completed in order (they can’t be done simultaneously). Determine and plot the probability mass function (PMF) for the total construction time of the project
Explanation / Answer
Let X be the total construction time of the project.
X can take the values:
2+3+5=10
2+3+7=12
2+4+5=11
2+4+7=13
3+3+5=11
3+3+7=13
3+4+5=12
3+4+7=14
-------------------------------------------
P(X=10) = (2,3,5) = 0.14
P(X=11) = (2,4,5) + (3,3,5) = 0.06 + 0.21 = 0.27
P(X=12) = (2,3,7) + (3,4,5) = 0.14 + 0.09 = 0.23
P(X=13) = (2,4,7) + (3,3,7) = 0.06 + 0.21 = 0.27
P(X=14) = (3,4,7) = 0.09
Cheers!
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.