A proposed nuclear power plant will cost $1.4 bilion to build and then will prod
ID: 2822949 • Letter: A
Question
A proposed nuclear power plant will cost $1.4 bilion to build and then will produce cash flows of $220 million a year for 15 years. After that period (in year 15), it must be decommissioned at a cost of $820 million, what is project NPV if the discount rate is 5%? what if it is 18%? (Negative amounts should be indicatad by a minus algn. Do not round intermediate calculationa. Entar your anewere In blions rounded to 3 decimal places.) Discount Rate 5% 1896 1.046 billion 3.823 billion Hints References eBook & Resources Hint #1Explanation / Answer
NPV at 5%
=-(1.4*1000)+((220*(1-(1+5%)^(-15)))/5%)-820/(1+5%)^15
=489.09 million or 0.489 bn
NPV at 18%
=-(1.4*1000)+((220*(1-(1+18%)^(-15)))/18%)-820/(1+18%)^15
=-348.34 million or -0.348 billion
the above is answer..
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.