10 The IRR of a project with an investment of $1 million is 10%. What is true of
ID: 2819550 • Letter: 1
Question
10 The IRR of a project with an investment of $1 million is 10%. What is true of the project's NPV if alternative investments have an 8% return? (A) (B) (C) (D) The NPV is zero The NPV is greater than zero The NPV is less than zero None of the above A project has an NPV of $1,250 at 12%. If you were to calculate the projects IRR, you should get a number bigger than 12% ? 11 True False 12 A project has an NPV of $1,250 at 12%. If you were to calculate the Project's Pl, will you get a number bigger than 1? Yes NoExplanation / Answer
10)
IRR is the rate at which net present value will be $0. It is the implied rate from the cash flows of the project. It is a cut off rate for the project. If the required return exceeds IRR, it should be rejected.
Hence, correct option is “B. The NPV is greater than ZERO”
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.