What is the IRR for each of these projects? (Do not round intermediate calculati
ID: 2818022 • Letter: W
Question
What is the IRR for each of these projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)
Using the IRR decision rule, which project should the company accept?
Project A
Project B
Yes
No
If the required return is 10 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)
Project A
Project B
At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
Bruin, Inc., has identified the following two mutually exclusive projects:
Explanation / Answer
Project A:
IRR = 16.13%
nPV = 3,198.96
Project B:
IRR = 16.02%
NPV = 4600.78
based on IRR choose A, based on NPV choose B
IRR rule is not always correct
Use IRR function in Excel for the cash flow = cash flow B - cash flow A
point of indifference = 15.75%
Discount rate 10.0000% Cash flows Year Discounted CF= cash flows/(1+rate)^year Cumulative cash flow (28,000.000) 0 (28,000.00) (28,000.00) 13,400.000 1 12,181.82 (15,818.18) 11,300.000 2 9,338.84 (6,479.339) 8,700.000 3 6,536.44 57.10 4,600.000 4 3,141.86 3,198.96Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.