Acubra Ltd uses a job-costing system at its Perth plant. The plant has a Machini
ID: 2817898 • Letter: A
Question
Acubra Ltd uses a job-costing system at its Perth plant. The plant has a Machining Department and an Assembly Department. Its job-costing system has two direct cost categories (direct materials and direct manufacturing labour) and two manufacturing overhead cost pools (the Machining Department overhead, allocated to jobs based on actual machine-hours, and the Assembly Department overhead allocated to jobs based on actual direct manufacturing labour costs). The 2017 budget for the plant is: Machining Assembly Manufacturing overhead Direct Manufacturing Labour costs Direct Manufacturing Labour hours Machine hours Department Department $1,900,000 $3,000,000 $1,400,000 $2,000,000 200,000 200,000 100,000 50,000 Required (1) During February, the job-cost record for job 501 contained the following Machining Assembly Direct materials used Direct Manufacturing Labour costs Direct Manufacturing Labour hours Machine hours Department Department $45,00070,000 $14,00015,000 1,500 1,000 1,000 2,000 Calculate the total costs of job 501 (2) At the end of 2017, the actual manufacturing overhead costs were $2 100 000 in Machining and 3 700 000 in Assembly. Assume that 55 000 actual machine-hours were used in the Machining Department and that actual direct manufacturing labour costs in the Assembly Department were $220 0000. Calculate the total over-or under-allocated manufacturing overhead.Explanation / Answer
Machine department overhead rate = Machine department overheads/Number of machine hours
= 1,900,000/50,000
= $38 per machine hour
Assembly department overhead rate = Assembly department overheads/Number of labor hours
= 3,000,000/200,000
= $15 per direct labor hour
(1) Calculation of cost of job 501
Total cost of job 501 = $242,500
(2)
Actual machine department overhead cost = $2,100,000
Actual machine hours = 55,000
Machine department overhead rate = $38 per machine hour
Allocated machine department overhead = Actual machine hours x Machine department overhead rate
= 55,000 x 38
= $2,090,000
Hence, under applied machine department overhad = Actual machine department overhead - Allocated machine department overhead
= 2,100,000 - 2,090,000
= $10,000
Actual assembly department overhead cost = $3,700,000
Actual labor hours = 55,000
Assembly department overhead rate = $15 per labor hour
For budgeted 200,000 labor hours, budgeted labor cost is $2,000,000.
Hence, budgeted labor cost per hour = 2,000,000/200,000
= $10
If actual labor cost is $2,200,000, thenactual labor hours must be = 2,200,000/10
= 220,000
Allocated assembly department overhead = Actual labor hours x Assembly department overhead rate
= 220,000 x 15
= $3,300,000
Hence, under applied assembly department overhad = Actual assembly department overhead - Allocated assembly department overhead
= 3,700,000 - 3,300,000
= $400,000
Total under applied manufacturing overhead = under applied machine department overhead + under applied assembly department overhead
= 10,000 + 400,000
= $410,000
Kindly give a positive rating if you are satisfied with the answer. Feel free to ask if you have any doubts. Thanks
Machining department Assembly department Total Direct material cost 45,000 70,000 115,000 Direct labor cost 14,000 15,000 29,000 Machining department overhead 2,000 x 38 = 76,000 76,000 Assembly department overhead 1,500 x 15 = 22,500 22,500 Total 242,500Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.