You are also considering another project which has a physical life of 3 years; t
ID: 2803775 • Letter: Y
Question
You are also considering another project which has a physical life of 3 years; that is, the machinery will be totally worn out after 3 years. However, if the project were terminated prior to the end of 3 years, the machinery would have a positive salvage value. Here are the project’s estimated cash flows:
Initial Investment End-of-Year
And Operating Net Salvage
Year Cash Flows Value
0 ($8,000) $8,000
1 3,900 5,100
2 3,000 2,500
3 2,550 0
Using the 8% cost of capital, what is the project’s NPV if it is operated for the full 3 years?
Would the NPV change if the company planned to terminate the project at the end of Year 2? At the end of Year 1?
What is the project’s optimal (economic) life?
** Please show all work! Send Excel screenshots. Thanks! **
Explanation / Answer
Initial investment = -8000
and the net salvage value if project lasts for:
3 years = 0
2 years = 2500
1 year = 5100
and this will be added to respective year Cashflow
Thus if the project lasts 3 years, Terminal year cashflow = 2550 + 0 = 2550
Thus if the project lasts 2 years, Terminal year cashflow = 3000 + 2500 = 5500
Thus if the project lasts 1 year, Terminal year cashflow = 3900 + 5100 = 9000
NPV at 8% cost of capital is as below:
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.